5 States Clear Land For Devoted Railway Freight Hall: Report

Facebook
Twitter
Google+
WhatsApp
Linkedin
Email


The approval got here after Piyush Goyal’s letter (File)

New Delhi:

Gujarat, Jharkhand, Uttar Pradesh, Bihar and Punjab have expedited land acquisition course of for the devoted freight corridors, days after Railway Minister Piyush Goyal wrote to 9 chief ministers, requesting them to clear hurdles within the challenge.

In his letter, Mr Goyal had informed the chief ministers that Prime Minister Narendra Modi was intently monitoring the progress of the Rs 81,000-crore challenge.

In a latest assembly, the Prime Minister’s Workplace had questioned the delay within the challenge, with its deadline being moved from December 2021 to June 2022.

Over the past seven days, the Railways has sorted out land acquisition points with these 5 states.

In Punjab, the Railways agreed to the state authorities’s proposal to permit it to borrow cash from the Devoted Freight Hall Company of India Restricted (DFCCIL) for the development of road-under bridges, whereas in sure areas of Bihar and Uttar Pradesh, it has coordinated with native authorities to deploy police power to cope with regulation and order points.

In Punjab, the long-pending land possession points for highway underneath bridges and highway over bridges at three areas have been resolved, Railways officers stated, whereas land points for building of excessive pressure line at two areas had been resolved.

In Bihar’s Rohtas district, three groups have been shaped to expedite fee and taking bodily possession of land, and police have been deployed at two highway over bridges which have been permitted, the officers stated.

In Jharkhand’s Giridh district, Rs 60 crore have been disbursed for land, whereas in Dhanbad, two acres of land which was caught has been acquired.

The challenge requires most land in Uttar Pradesh.

In Kanpur, it has acquired the long-stuck 80-m lengthy piece of land wanted for an strategy highway for a highway underneath bridge, whereas the remaining 40-metre shall be acquired by September 15, the officers stated.

A five-km patch in Saharanpur district which was caught for over 2.5 years because of regulation and order points was additionally cleared and possession taken by the Railways on September 6, they stated, including related caught land patches within the state had been additionally cleared.

In Gujarat too, three highway over bridges in Bharuch and 7 in Surat have been awarded.

To place the Railways’ freight challenge so as, Mr Goyal held a number of assembly stakeholders and officers to expedite the progress and resolve important problems with the DFC over the previous 10 days.